{"id":7155,"date":"2022-10-31T15:23:00","date_gmt":"2022-10-31T20:23:00","guid":{"rendered":"https:\/\/projectmanagementacademy.net\/resources\/?p=7155"},"modified":"2022-10-31T15:23:03","modified_gmt":"2022-10-31T20:23:03","slug":"introduction-to-schedule-network-analysis","status":"publish","type":"post","link":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/","title":{"rendered":"Introduction to Schedule Network Analysis"},"content":{"rendered":"\n<p>A Project Management Professional (PMP)\u00ae credential holder can create a schedule network diagram, conduct schedule network analysis, and use the critical path method to manage the schedule toward desired results.<\/p>\n\n\n\n<p><strong>On this page:<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\"><li><a href=\"#introduction\">Introduction to Schedule Network Analysis<\/a><\/li><li><a href=\"#snd\">What is a Schedule Network Diagram?<\/a><\/li><li><a href=\"#best-practices\">Best Practices for Schedule Network Analysis<\/a><\/li><li><a href=\"#prioritize\">Why Schedule Network Analysis Should Be Prioritized<\/a><\/li><li><a href=\"#summary\">Summary<\/a><\/li><\/ul>\n\n\n\n<div class=\"wp-block-columns has-background is-layout-flex wp-container-core-columns-is-layout-1 wp-block-columns-is-layout-flex\" style=\"background-color:#f3fbff\">\n<div class=\"wp-block-column is-layout-flow wp-block-column-is-layout-flow\" style=\"flex-basis:40%\">\n<div style=\"height:60px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<div class=\"wp-block-image\"><figure class=\"alignright size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"720\" height=\"600\" src=\"https:\/\/e360-media.s3.amazonaws.com\/2022\/09\/01094754\/Emotional-Intelligence-Free-PDU-Course.jpg\" alt=\"Free Course on Emotional Intelligence\" class=\"wp-image-6604\" srcset=\"https:\/\/e360-media.s3.amazonaws.com\/2022\/09\/01094754\/Emotional-Intelligence-Free-PDU-Course.jpg 720w, https:\/\/e360-media.s3.amazonaws.com\/2022\/09\/01094754\/Emotional-Intelligence-Free-PDU-Course-300x250.jpg 300w\" sizes=\"auto, (max-width: 720px) 100vw, 720px\" \/><\/figure><\/div>\n<\/div>\n\n\n\n<div class=\"wp-block-column is-layout-flow wp-block-column-is-layout-flow\" style=\"flex-basis:50%\">\n<div style=\"height:48px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<p><\/p>\n\n\n\n<p class=\"has-medium-font-size\" id=\"block-eef25254-e22e-41f6-826b-cab064e3d095\"><strong>Free Emotional Intelligence PDU<\/strong><\/p>\n\n\n\n<p id=\"block-14690051-2796-4b03-bcb7-95d54bd01fcd\"><em>Develop your Emotional Intelligence as well as your team members in this Free PDU Course!<\/em><\/p>\n\n\n\n\t\t\t\t\t<script>\n\t\t\t\t\t\thbspt.enqueueForm({\n\t\t\t\t\t\t\tportalId: 3294842,\n\t\t\t\t\t\t\tformId: \"9513deed-dab2-44ea-a7fb-33297ddc13b6\",\n\t\t\t\t\t\t\ttarget: \"#hbspt-form-1775336693000-3083103252\",\n\t\t\t\t\t\t\tregion: \"na1\",\n\t\t\t\t\t\t\t\n\t\t\t\t\t\t});\n\t\t\t\t\t<\/script>\n\t\t\t\t\t<div class=\"hbspt-form\" id=\"hbspt-form-1775336693000-3083103252\"><\/div>\n<\/div>\n\n\n\n<div class=\"wp-block-column is-layout-flow wp-block-column-is-layout-flow\"><\/div>\n\n\n\n<div class=\"wp-block-column is-layout-flow wp-block-column-is-layout-flow\" style=\"flex-basis:10%\">\n<div style=\"height:100px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n<\/div>\n<\/div>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"introduction\"><strong>Introduction to Schedule Network Analysis<\/strong><\/h2>\n\n\n\n<p>Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.<\/p>\n\n\n\n<p>The project activity sequence is used to create a network diagram to visualize the project activities that must be completed to reach the project\u2019s goals. High-priority activities may be elements found on the critical path, the sequence of activities representing the longest path through a project. The project manager conducts schedule network analysis to identify potential bottlenecks and risks to the timeline.<\/p>\n\n\n\n<p>Schedule network analysis and critical path are potential topics within Project Management Institute (PMI) PMP\u00ae certification exam. Informal labels include \u201cschedule network analysis technique PMP\u201d or \u201cschedule network analysis PMP.\u201d<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"snd\"><strong>What is a Schedule Network Diagram?<\/strong><\/h2>\n\n\n\n<p>A schedule network diagram is a graphical representation of the project\u2019s activities. Begin on the left with the project start, and work right towards documenting all project activities until you reach the project end. Activities are mapped out in the order of planned occurrence, left to right, with arrows to connect dependent activities. You can use project management <a href=\"https:\/\/support.microsoft.com\/en-us\/office\/create-a-network-diagram-in-project-desktop-a3e8cc62-27c5-4e94-aaab-6fbc470b6d33\" target=\"_blank\" rel=\"noreferrer noopener\">software to generate a schedule network diagram<\/a>.<\/p>\n\n\n\n<p>A schedule network diagram is a graphical representation of the project\u2019s activities. Begin on the left with the project start, and work right towards documenting all project activities until you reach the project end. Activities are mapped out in the order of planned occurrence, left to right, with arrows to connect dependent activities. You can use project management software to generate a schedule network diagram.<\/p>\n\n\n\n<div class=\"wp-block-image\"><figure class=\"aligncenter size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"782\" height=\"300\" src=\"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132320\/image.png\" alt=\"\" class=\"wp-image-7156\" srcset=\"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132320\/image.png 782w, https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132320\/image-300x115.png 300w, https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132320\/image-768x295.png 768w\" sizes=\"auto, (max-width: 782px) 100vw, 782px\" \/><figcaption>Schedule Network Diagram<\/figcaption><\/figure><\/div>\n\n\n\n<p>Include information such as duration, time lags, or float between activities to enhance the project manager\u2019s ability to do an analysis. Use a schedule network diagram, with regular diagram updates, to monitor changes to the <a href=\"https:\/\/projectmanagementacademy.net\/resources\/blog\/schedule-management-plan\/\" target=\"_blank\" rel=\"noreferrer noopener\">project\u2019s schedule<\/a>, paying particular attention to the critical path.<\/p>\n\n\n\n<p>The critical path is the longest activity sequence needed to complete the project, which is always the longest sequence of tasks or activities. Project managers need to know the critical path to make informed schedule decisions.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"best-practices\"><strong>Best Practices for Schedule Network Analysis<\/strong><\/h2>\n\n\n\n<p>Think of these best practices as a Schedule Network Analysis checklist:<\/p>\n\n\n\n<ol class=\"wp-block-list\" type=\"1\"><li>Have a clear understanding of project objectives and scope to identify the duration of project tasks<\/li><li>Work with your team to create a detailed project schedule with all tasks, milestones, and dependencies<\/li><li>Use software to visualize the network diagram for easier identification of the critical path and potential risks<\/li><li>Regularly update the network diagram during the project to better identify changes and make adjustments<\/li><li>Communicate analysis results to your team and stakeholders, so everyone understands the importance of monitoring the critical path to avoid risks and schedule delays<\/li><\/ol>\n\n\n\n<hr class=\"wp-block-separator is-style-wide\"\/>\n\n\n\n<div class=\"wp-block-group is-layout-flow wp-block-group-is-layout-flow\">\n<p class=\"has-text-align-center has-medium-font-size\"><strong>Studying for the PMP Exam?<\/strong><\/p>\n<\/div>\n\n\n\n<div class=\"wp-block-buttons is-horizontal is-content-justification-center is-layout-flex wp-container-core-buttons-is-layout-1 wp-block-buttons-is-layout-flex\">\n<div class=\"wp-block-button has-custom-width wp-block-button__width-100 is-style-fill\"><a class=\"wp-block-button__link has-white-color has-text-color has-background\" href=\"https:\/\/projectmanagementacademy.net\/free-pmp-questions\" style=\"border-radius:2px;background-color:#366194\" target=\"_blank\" rel=\"noreferrer noopener\">PMP Practice Questions<\/a><\/div>\n<\/div>\n\n\n\n<div style=\"height:8px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<hr class=\"wp-block-separator is-style-wide\"\/>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"prioritize\"><strong>Why Schedule Network Analysis Should Be Prioritized<\/strong><\/h2>\n\n\n\n<p>Risks of not conducting schedule network analysis include:<\/p>\n\n\n\n<ul class=\"wp-block-list\"><li>delays if critical tasks are not completed on time<\/li><li>budget increases from unexpected costs<\/li><li>failure to meet project objectives if critical milestones are not achieved<\/li><li>demoralization and demotivation of the team due to a lack of clarity on the project&#8217;s critical path<\/li><\/ul>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"summary\"><strong>Summary<\/strong><\/h2>\n\n\n\n<p>A schedule network diagram is a graphical representation of the critical path of a project. Schedule network diagrams can be generated by software or simply sketched by hand. The schedule network analysis technique is used to understand the project\u2019s critical path. PMP credential holders know that by understanding the critical path, they can better prioritize tasks and identify schedule risks.<\/p>\n\n\n\n<div style=\"height:45px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<div class=\"wp-block-group\"><div class=\"wp-block-group__inner-container is-layout-flow wp-block-group-is-layout-flow\">\n<p style=\"font-size:25px\"><strong>Upcoming PMP Certification Training &#8211; Live &amp; Online Classes<\/strong><\/p>\n\n\n\n<div class=\"wp-block-group\"><div class=\"wp-block-group__inner-container is-layout-flow wp-block-group-is-layout-flow\"><table class=\"table table-striped table-bordered table-responsive-sm font-md mt-5 mb-0 d-none d-md-table\"><tr><td>Name<\/td><td>Date<\/td><td>Place<\/td><td><\/td><\/tr><\/table>\n<\/div><\/div>\n\n\n\n<p><\/p>\n<\/div><\/div>\n\n\n\n<div style=\"height:45px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<hr class=\"wp-block-separator is-style-wide\"\/>\n\n\n\n<div style=\"height:25px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n","protected":false},"excerpt":{"rendered":"<p>A Project Management Professional (PMP)\u00ae credential holder can create a schedule network diagram, conduct schedule network analysis, and use the critical path method to manage the schedule toward desired results. On this page: Introduction to Schedule Network Analysis What is a Schedule Network Diagram? Best Practices for Schedule Network Analysis Why Schedule Network Analysis Should [&hellip;]<\/p>\n","protected":false},"author":2,"featured_media":7157,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[98],"tags":[],"class_list":["post-7155","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-scheduling"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v24.0 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Schedule Network Analysis in Project Management<\/title>\n<meta name=\"description\" content=\"Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Schedule Network Analysis in Project Management\" \/>\n<meta property=\"og:description\" content=\"Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/\" \/>\n<meta property=\"og:site_name\" content=\"Project Management Academy Resources\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/ProjectManagementAcademy.net\" \/>\n<meta property=\"article:published_time\" content=\"2022-10-31T20:23:00+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2022-10-31T20:23:03+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png\" \/>\n\t<meta property=\"og:image:width\" content=\"782\" \/>\n\t<meta property=\"og:image:height\" content=\"200\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Kyle Puckett\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@PM_Academy\" \/>\n<meta name=\"twitter:site\" content=\"@PM_Academy\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Kyle Puckett\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/\",\"url\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/\",\"name\":\"Schedule Network Analysis in Project Management\",\"isPartOf\":{\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png\",\"datePublished\":\"2022-10-31T20:23:00+00:00\",\"dateModified\":\"2022-10-31T20:23:03+00:00\",\"author\":{\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/#\/schema\/person\/68bbacbe3d69e983543ed1d184a6cd82\"},\"description\":\"Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.\",\"breadcrumb\":{\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#primaryimage\",\"url\":\"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png\",\"contentUrl\":\"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png\",\"width\":782,\"height\":200,\"caption\":\"Schedule Network Analysis in Project Management\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/projectmanagementacademy.net\/resources\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Introduction to Schedule Network Analysis\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/#website\",\"url\":\"https:\/\/projectmanagementacademy.net\/resources\/\",\"name\":\"Project Management Academy Resources\",\"description\":\"Get the latest industry news, trends, and insights you need to be the most effective Project Manager.\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/projectmanagementacademy.net\/resources\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Person\",\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/#\/schema\/person\/68bbacbe3d69e983543ed1d184a6cd82\",\"name\":\"Kyle Puckett\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/projectmanagementacademy.net\/resources\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/1b2b4b0927c02229f63c6d1b77cd51e1?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/1b2b4b0927c02229f63c6d1b77cd51e1?s=96&d=mm&r=g\",\"caption\":\"Kyle Puckett\"},\"url\":\"#molongui-disabled-link\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Schedule Network Analysis in Project Management","description":"Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/","og_locale":"en_US","og_type":"article","og_title":"Schedule Network Analysis in Project Management","og_description":"Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.","og_url":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/","og_site_name":"Project Management Academy Resources","article_publisher":"https:\/\/www.facebook.com\/ProjectManagementAcademy.net","article_published_time":"2022-10-31T20:23:00+00:00","article_modified_time":"2022-10-31T20:23:03+00:00","og_image":[{"width":782,"height":200,"url":"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png","type":"image\/png"}],"author":"Kyle Puckett","twitter_card":"summary_large_image","twitter_creator":"@PM_Academy","twitter_site":"@PM_Academy","twitter_misc":{"Written by":"Kyle Puckett","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/","url":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/","name":"Schedule Network Analysis in Project Management","isPartOf":{"@id":"https:\/\/projectmanagementacademy.net\/resources\/#website"},"primaryImageOfPage":{"@id":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#primaryimage"},"image":{"@id":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#primaryimage"},"thumbnailUrl":"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png","datePublished":"2022-10-31T20:23:00+00:00","dateModified":"2022-10-31T20:23:03+00:00","author":{"@id":"https:\/\/projectmanagementacademy.net\/resources\/#\/schema\/person\/68bbacbe3d69e983543ed1d184a6cd82"},"description":"Schedule network analysis is a vital project management scheduling technique, in addition to the schedule network diagram tool and the critical path method.","breadcrumb":{"@id":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#primaryimage","url":"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png","contentUrl":"https:\/\/e360-media.s3.amazonaws.com\/2022\/10\/31132923\/Schedule-Network-Analysis-in-Project-Management.png","width":782,"height":200,"caption":"Schedule Network Analysis in Project Management"},{"@type":"BreadcrumbList","@id":"https:\/\/projectmanagementacademy.net\/resources\/blog\/introduction-to-schedule-network-analysis\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/projectmanagementacademy.net\/resources\/"},{"@type":"ListItem","position":2,"name":"Introduction to Schedule Network Analysis"}]},{"@type":"WebSite","@id":"https:\/\/projectmanagementacademy.net\/resources\/#website","url":"https:\/\/projectmanagementacademy.net\/resources\/","name":"Project Management Academy Resources","description":"Get the latest industry news, trends, and insights you need to be the most effective Project Manager.","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/projectmanagementacademy.net\/resources\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/projectmanagementacademy.net\/resources\/#\/schema\/person\/68bbacbe3d69e983543ed1d184a6cd82","name":"Kyle Puckett","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/projectmanagementacademy.net\/resources\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/1b2b4b0927c02229f63c6d1b77cd51e1?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/1b2b4b0927c02229f63c6d1b77cd51e1?s=96&d=mm&r=g","caption":"Kyle Puckett"},"url":"#molongui-disabled-link"}]}},"_links":{"self":[{"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/posts\/7155","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/comments?post=7155"}],"version-history":[{"count":4,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/posts\/7155\/revisions"}],"predecessor-version":[{"id":7171,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/posts\/7155\/revisions\/7171"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/media\/7157"}],"wp:attachment":[{"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/media?parent=7155"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/categories?post=7155"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/projectmanagementacademy.net\/resources\/wp-json\/wp\/v2\/tags?post=7155"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}