New Horizons New Horizons Project Management Academy Project Management Academy Six Sigma Online Six Sigma Online Velopi Velopi Watermark Learning Watermark Learning
Educate 360
Educate 360 Educate 360
Project Management Academy
To receive your FREE test answers and complete explanations please submit your contact information and agree to our privacy policy.

Free PMP® Exam Practice Questions

Project Management Academy’s free PMP exam practice questions are based on relevant A Guide to the Project Management Body of Knowledge (PMBOK® Guide) topics. Below you will find 50 PMP exam questions to help prepare you for the PMP exam. Upon completion please enter your information in the fields below to access the results and complete explanations.

If you are a Project Management Academy student, you can login to access over 2,000 free PMP exam questions utilizing our realistic online PMP exam simulator software. This access is free with the purchase of any of our PMP certification courses.


1. Which of the following techniques could you apply, to any project in any industry, as a way of objectively measuring project progress?

A. Microsoft Project
B. Earned value analysis
C. Percent complete
D. Clear communication of requirements

2. Your project has a vendor that is under a firm fixed price contract and the seller has filed a claim. Which of the following is the preferred method of settling this dispute?

A. Litigation
B. Negotiation
C. Mediation
D. Arbitration

3. You just completed your weekly project status meeting. In this meeting, you received information from the team regarding actual engagement levels of stakeholders. One of your key stakeholders has ceased supporting the project and is calling for its termination. Which of the following is a true statement about this information?

A. This information should be given directly to the project sponsor so they can stop this stakeholder from terminating the project
B. This information is of little value of the project sponsor because they were in the meeting they should know where the project stands
C. This information should be analyzed then placed into a report for the project sponsor to gain a clear understanding of the impact
D. This information should be given directly to the project team at the next team meeting

4. Which of the following becomes increasingly important when working with virtual teams?

A. Work assignments
B. Communications
C. Budget
D. Schedule

5. Your team has developed a strategy to set aside $1000 in a contingency budget and an extra week in the schedule, in the event a particular risk occurs on the project. What is the best description of this strategy?

A. Acceptance
B. Escalation
C. Mitigation
D. Avoidance

6. As the project manager you have decided to separate the sources of risk by phase and by the WBS. Using this technique you will find the riskiest areas of the project. Which of the following best describes the technique employed?

A. Risk categorization
B. Proper risk planning
C. Risk urgency
D. Risk data quality assessment

7. As a new Project Manager in a large Healthcare IT company, you are asked to identify risks for your newly assigned project. This should result in the creation of which project document?

A. Risk Management Plan
B. Risk Register
C. Risk Breakdown Structure
D. Risk versus Reward

8. You are the project manager for a project with 200 stakeholders. The team identified five individuals as key stakeholders. You are developing the stakeholder engagement plan, which is an actionable blueprint of how to interact with the stakeholders to support the project objectives. You will base the actions taken on an analysis of key stakeholder needs, their level of interest, and their potential impact on project success. Where will you find this information to analyze?

A. Project charter
B. Project management plan
C. Files located in the human resource department
D. Stakeholder register

9. Which of the following is included in the total project budget but is not included in the cost performance baseline?

A. Control accounts
B. Work package estimates
C. Contingency reserves
D. Management reserves

10. When considering influences that could have an impact on cost management which of the following would you be the least concerned about?

A. Financial control procedures
B. Organizational culture and structure
C. The proposed budget
D. Marketplace conditions, i.e. currency exchange rates, products, and services available

11. You are the project manager for a major construction project. You have just completed a walk through with the construction superintendent, when they tell you that one of the critical path activities will be two weeks late. Upon further discussion you find out the underlying reason for this. What project management tool are you using?

A. Interpersonal Skills
B. Face-To-Face Communication
C. General Management Skills
D. Variance Analysis

12. Once the network diagram is complete, how many activities or milestones will not have both a predecessor and a successor?

A. 1
B. 1 in each phase
C. As many as necessary
D. 2 in the entire network

13. Which of the following is a true statement regarding the schedule management plan?

A. It may or may not be written depending on the project management approach of the company executives
B. It can be formal or informal, highly detailed or broad in nature depending on the project, and it is a key input to the Define Activities process
C. It must be formal and highly detailed prior to project management plan approval
D. It requires the input of all stakeholders involved in the project and those that will eventually approve the plan

14. In your project for the design and development of a new, ultra high speed hard drive, the team has defined certain information for the quality control department to use as a quality control check. The quality control department will check the data access time of each hard drive. In order to pass the quality test each drive must transfer 1 GB of data in 500 ms (plus or minus 100 ms). Which of the following terms best describes this information?

A. Quality checklist
B. Control limits
C. Attribute limits
D. Quality metric

15. Your project team has been executing based on the project plan and is gathering the verified deliverables before planning to meet with the customer. What is the primary purpose of this meeting?

A. To ensure that all of the approved scope has been included in the project
B. To validate that the final product met the quality requirements
C. To test the final product
D. To gain formal acceptance of the deliverables from the customer or sponsor

16. Which of the following items organizes and defines the total scope of the project and depicts the work specified in the currently approved version of the project scope statement?

A. Project Statement of Work
B. Work Breakdown Structure (WBS)
C. Product Breakdown Structure (PBS)
D. Scope Development Chart

17. All of the following are elements of the requirements management plan except which one?

A. Requirements of the project
B. Processes for how requirements will be collected, tracked, and prioritized
C. Process for how changes to the product will be initiated
D. Product metrics and the reasons for using them

18. The project management plan may be changed without a change request only under which of the following circumstances?

A. The plan has been written by the project manager and no team member input is included
B. The plan has been written but not approved by the sponsor
C. The sponsor has approved the plan but the project has not yet started
D. The plan has been approved by the sponsor but not yet implemented

19. The chief financial officer, who happens to be your project sponsor, has just called you into their office to discuss a requested change in your project. After asking you several questions, the project sponsor tells you to implement the change. What is the next thing you should do?

A. Implement the change
B. Send the change request to the change control board for approval
C. Fill out a change request form and request a signature from the project sponsor.
D. Evaluate the impact of the change on the time, cost, scope, quality, and risk objectives of the project

20. The project manager wants all of the prospective contractors, who are expected to submit proposals on a new project, to have a clear understanding of the requirements of the procurement. The project manager decides to hold a meeting to describe the upcoming procurement event. What is the best description of this meeting?

A. Proposal Evaluation Techniques
B. Bidders Conference
C. Screening System
D. Procurement Negotiations

21. Using of which of the following contract types will cause the seller to have the most risk?

A. Fixed Price
B. Cost Reimbursable
C. Time and Materials
D. Cost Plus a Percentage of Cost

22. The project manager may call on which of the following individuals to assist in managing difficult stakeholders as needed?

A. Project sponsor
B. Senior executive
C. Assistant project manager
D. Project team member

23. You're the project manager for a construction project. The project team identified a rainstorm as a possible risk. When the prediction of an approaching storm was announced the response plan was implemented, which included having sandbags on hand to reduce the impact of flooding on the site. Halfway through preparations to respond to this risk the project manager is informed that not enough sandbags were ordered. Who is the person informing the project manager of this?

A. Risk Owner
B. Risk Response Manager
C. Risk Manager
D. Assistant Project Manager

24. From an organizational perspective, managing project knowledge entails which of the following?

A. Documenting lessons learned
B. Storing information for use by future projects
C. Ensuring the experience, skills, and expertise are used before, during, and after a project
D. All of the above

25. Your project was recently terminated early. As the project manager you must review which of the following?

A. All prior information from previous phase closures
B. Project Management Plan
C. The contract
D. All of the above

26. You have just been named the project manager for a new information technology project. Your sponsor has heard of an innovative approach to project management called agile and wants you to investigate. You are familiar with agile and explained that you would conduct a suitability assessment and report back on your findings. What three areas are you looking at?

A. Culture, the project itself and the team
B. Technology, funding, and management style
C. The length of the project, infrastructure, and funding
D. Funding, technology, and the length of the project

27. Your project team is using an iteration based approach to a software development project. You are attending a meeting where the development team is asking questions about the requirements, getting clarification on the Definition of Done and estimating how much work they can finish in the upcoming iteration. What meeting are you attending?

A. The Scope Planning Meeting
B. The Daily Stand Up Meeting
C. The Sprint Retrospective
D. The Sprint Planning Meeting

28. You are using an iteration based agile approach to a software development project. You decided to use this approach because the sponsor knew the high level capabilities but were unable to provide a detailed list of requirements. At a recent status meeting the sponsor asks if you can provide an estimate of what capabilities will be delivered and when that will occur. What is the best document to provide?

A. Sprint planning Log
B. Scope Statement
C. Product Roadmap
D. Sprint burndown chart

29. Your colleague is new to agile and wants to learn more about it. You explain that agile is really a mindset that is established by following four paired values and 12 principles. What is the document that you are describing?

A. Agile Core Principles
B. Scrum Allegiance Pledge
C. Software Declaration
D. Agile Manifesto

30. You are the project manager for the XYZ project. This a complex project involving the installation of hardware in a data center and the development of a new software application. The hardware installation requires a very specific process be followed and has fixed requirements. The software portion has known features, but the specific requirements are not documented. What is the most likely project approach given these facts?

A. Agile
B. Hybrid
C. Predictive
D. Collaborative

31. You are new to agile methodologies, so you reach out to an experienced project manager for guidance. She explains that one of the primary differences between agile and a predictive project is the leadership approach of the project manager. In a predictive project, the project manager directs work at the start of the project while the agile project manager encourages and coaches the team to be self-directed. The leadership style of removing barriers, creating an environment of collaboration and encouragement of a self-directed team is called?

A. Servant Leadership
B. Laissez-faire Leadership
C. Egalitarian Leadership
D. Control Leadership

32. You have just completed your Sprint Review meeting and the Product Owner is not satisfied with the results. They state that they will not accept the software and will re-adjust the Product Backlog. The team facilitator suggests that the Product Owner attend a meeting to discuss what could be improved to stop this from occurring in the next sprint. They are most likely inviting the Product Owner to what meeting?

A. Sprint Planning
B. Lessons Learned
C. Retrospective
D. Daily Scrum

33. Your sponsor is curious about the progress of your project team. They ask if you have any charts that could help them understand your progress in reaching the sprint goal, and you assure them you do. You will most likely provide them with what agile tool?

A. Burndown Chart
B. Retrospective analysis
C. Monte Carlo Analysis
D. Schedule Network Diagram

34. Your project team has been working for several months on a new software application designed to increase productivity for the call center representatives. The Product Owner has accepted the results of your sprints, and you are now ready to do final testing. During user testing, you are surprised to hear that both the end users and the sponsor are disappointed in your software as delivered. How could you have potentially avoided this?

A. Document and baseline the requirements
B. Invite the sponsor and select end users to the sprint review meeting.
C. Used a flow based agile approach
D. Let the Product Owner do the acceptance testing as they approved all the work so far.

35. Your company has just decided they could gain a competitive advantage by adopting agile methodologies, so they sent you to Scrum Master training. You have just returned from the training, and the PMO calls you for a discussion. They have a new project they believe would be a great opportunity to try agile and want your thoughts on what the next step should be. What are you most likely to recommend?

A. Use a traditional approach. Agile can take years to figure out.
B. Identify key stakeholders and start gathering requirements
C. Provide training on agile methodologies and approaches
D. Start your sprint planning. Agile is about speed to market.

36. Your team is working on a project to provide research capabilities to a wide variety of users. You have successfully completed several sprints, but at the last daily stand up meeting several team members identified a problem with stakeholders interrupting their work with requests for status reports. Specifically, they wanted to know what they were working on and inquiring about the progress of the sprint. What could have avoided this problem?

A. Nothing. This is not a problem as Agile is focused on high levels of customer interaction.
B. Use of Schedule Network Diagrams
C. Use of Epics
D. Use of Information Radiators

37. The project you were assigned to has recently delivered a highly successful product, and you are preparing for your next project. A colleague who is unfamiliar with agile has heard about story points but does not understand how they are used. What should you tell him?

A. Each story point is equal to 5 hours development work.
B. They are an arbitrary unit of measure designed to estimate the relative difficulty of a task or user story.
C. Story points are used to count the total number of user stories in a sprint and are tracked on a Kanban chart.
D. Story points are based on the Pythagorean sequence and are used to determine the risk associated with the next sprint.

38. You have just been assigned a software project and are considering adopting the Scrum methodology, but you are concerned that the project will require many developers working on a highly integrated product. You decide to conduct an Agile Suitability Assessment to ensure that Scrum is the correct approach. What is not a factor you will consider?

A. The project funding
B. The organizational culture
C. The nature of the project itself
D. The size and training of the team

39. You have just been assigned a software project and are considering adopting the Scrum methodology for delivery. You know the maximum size for a Scrum team is 9 developers, but this project will require at least 3 times that to meet the externally imposed deadline. You discuss this with the Scrum Master, and he suggests that there is a technique to coordinate deliverables across several Agile teams. What did he likely suggest?

A. Flow based agile management
B. Product Backlog controls
C. Monte Carlo controls
D. Scrum of Scrums

40. One of your project managers is confused about Agile. They understand Agile is a mindset based on the Agile Manifesto 4 Paired Values and 12 Principles. They are confused because they keep hearing about different agile approaches like Scrum, XP, and Lean. You explain that within this framework, every agile team needs to identify their unique __________.

A. Flow of Flows
B. Kanban Tempo
C. Way of Working
D. Baseline

41. You are new to agile and are confused about the Kanban board. The Kanban board contains all the work committed to for the current sprint, as well as the status of the work. You ask the Agile Coach to help you understand how the Kanban board is used, and they explain it to you. Which of the following is not a use of the Kanban board?

A. Provides a visual to show what everyone is working on
B. Assign work to the team based on their workload
C. Helps estimate the likelihood of meeting the sprint goal
D. Can be used as an information radiator

42. You are the team facilitator and are listening to the Daily Scrum. The team is facing several challenges, including technical challenges and an unresponsive stakeholder. Those challenges are now threatening the ability of the team to achieve the sprint goal. How should you proceed?

A. Identify the impediments to team progress and help remove them, including contacting the unresponsive stakeholder.
B. Since the sprint goal may not be met, elevate the issue immediately to the sponsor.
C. Determine the best way to work around the issues and direct the team accordingly.
D. Nothing. This is a self-directed team, and they need to figure out what the next steps are.

43. Based on the continuum of project methodologies, an adaptive approach is both:

A. Continuous and integrated
B. Iterative and incremental
C. Self-directed and self-managed
D. Hybrid and waterfall

44. You have just completed your Agile training and are confident you know all there is to know about the topic. You are discussing it with a senior Scrum Master and mention that all Agile approaches are based on Scrum and use a backlog. He explains that there is another approach that does not use a backlog, but it does normally use a tool that is common to backlog based Agile. He is most likely describing what?

A. Sprint
B. Retrospective
C. Kanban
D. Baseline

45. Your team is developing an application to increase the productivity of the employees in your regional call center. Your team has been working closely with the Product Owner to ensure all the features planned for the next release were completed. Suddenly your lead developer informs you that there is a group of requirements that were missed, and the deployment must be delayed several months as they work through them. The system cannot go live without them. What type of requirement did you likely miss?

A. Compliance
B. Functional
C. Business
D. Project

46. Story points are often used by agile teams to determine the level of effort for a user story or task. After several sprints, the Scrum Master would like to forecast when the next release in the Product Roadmap will be ready, and does this by averaging the number of story points in all of the prior team sprints and comparing that to the work remaining in the product backlog. The average number of story points an Agile team is completing in their sprints is referred to as what?

A. Throughput
B. Cycle Time
C. Telemetry
D. Velocity

47. Your Agile team is working on a new order fulfilment system for their client. Their customer does not know exactly how they want the system to function, but they do know the features that will deliver the highest business value. You use those features to develop a high-level schedule of what functionality will be delivered and roughly when it will be delivered. You have just completed the _________ ___________.

A. Product Roadmap
B. Product Backlog
C. Product Baseline
D. Agile schedule

48. You conducted an analysis of the progress of your team. You realize that at the current pace of development, the estimated date of the next release will be delayed substantially. You approach the Agile Coach about the possibility of approving overtime so the team can get back on track. To your surprise, they disagree with that approach. They state that approving overtime or applying additional resources violates one of the principles of the Agile Manifesto. Which principle did it violate?

A. At regular intervals, the team readjusts their commitments based on actual performance.
B. Agile processes promote sustainable development.
C. The Kanban Board is the primary measure of progress
D. Build projects around motivated individuals. Whatever they say is the law.

49. You have just completed discussing your project with a colleague who is using a waterfall approach on his project. You are curious about their use of Earned Value to use current project performance as a basis for forecasting future performance. You wonder if Earned Value can be used for an Agile project, so you ask your Scrum Master. They state:

A. No, because we do not measure completed work in Agile
B. Yes, but you can not determine Earned Value, Planned Value or Actual Cost
C. Yes, you can use Earned Value for an Agile project.
D. Yes, but it is impossible to compute CV and SV.

50. You have assembled your Agile team and are beginning to determine your Way of Working. You hold a meeting to discuss what method you will use to estimate, establish team norms and coordinate with the product owner. What is this initial meeting called?

A. Planning Poker
B. Forecasting sprint
C. Original Sprint
D. Sprint 0

To receive your FREE test answers and complete explanations please submit your contact information and agree to our privacy policy.
processing

7 Secrets to Passing the PMP Exam

Want to pass the PMP Certification Exam?

Download this free guide and pass your PMP exam!

Live Classroom PMP Exam Prep Courses

Find a PMP Course Near Me
Select a city, or view all course options.

Recommended Locations

Live Classroom PMP Training
2025 Live PMP Training Courses
Jan 21,22,23,24
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Mar 31, Apr 1,2,3
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
May 19,20,21,22
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jul 21,22,23,24
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Sep 15,16,17,18
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Nov 3,4,5,6
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
2024 Online PMP Training Courses
Nov 23,24 & 30, Dec 1
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 2,3,4,5
8:30am-6:00pm
$2,895 USD
$1,995 USD
COURSE FULL
Dec 3,4 & 10,11
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 7,8 & 14,15
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
8:00am-12:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
6:00pm-10:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
1:00pm-5:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9,10,11,12
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 12,13 & 19,20
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 16,17,18,19
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
2025 Online PMP Training Courses
Jan 2,3 & 9,10
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 4,5 & 11,12
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6,7,8,9
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6-9 & 13-16
6:00pm-10:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6-9 & 13-16
8:00am-12:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6-9 & 13-16
1:00pm-5:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 7,8 & 14,15
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 11,12 & 18,19
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 13,14,15,16
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 18,19 & 25,26
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Columbus PMP Certification Training
5 Star Rating
Rated 5/5 based on 5,717 reviews
2024 Online PMP Training Courses
Dec 2,3,4,5
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 7,8 & 14,15
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
3:00pm-7:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
5:00am-9:30am
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
10:00am-2:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9-12 & 16-19
6:00pm-10:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 9,10,11,12
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Dec 16,17,18,19
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
2025 Online PMP Training Courses
Jan 4,5 & 11,12
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6,7,8,9
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6-9 & 13-16
10:00am-2:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6-9 & 13-16
5:00am-9:30am
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 6-9 & 13-16
3:00pm-7:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 27,28,29,30
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Jan 27-30 & Feb 3-6
5:00am-9:30am
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Feb 1,2 & 8,9
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Feb 3,4,5,6
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Feb 10,11,12,13
8:30am-6:00pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Feb 10-13 & 17-20
10:00am-2:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
Feb 10-13 & 17-20
3:00pm-7:30pm
$2,895 USD
$1,995 USD
$2,895 USD   $1,995 USD
VOD PMP Exam Prep
Video On Demand
Video on Demand
At your own pace
$995 USD
REGISTER
$995 USD
Unsure of the date or location?
now and decide later.
Endorsed IIBA Certification Training Provider
Project Management Academy BBB Business Review
100% Money Back Guarantee
Authorize Seal Credit Card Processing
Top 10 Elearning Courses 2021

7 Secrets to Passing the PMP Exam

Want to pass the PMP Certification Exam?

Download this free guide and pass your PMP exam!